HC rejects petitions against nuclear plant in Haryana village #WTFnews


TNN | May 17, 2013, 09.09

A division bench of the HC comprising Justice A K Mittal and Justice G S Sandhawalia passed these orders while giving reference to recent supreme court judgment, giving a go-ahead for Kudankulam nuclear power plant in Tamil Nadu, in which SC had observed that such plants are set up for the welfare of people and for sustainable growth.

In the Kudankulam case, the apex court in its May 6 orders had also observed that development of nuclear energy is important for India and allowing the plant is in larger public interest.

The development is significant, as a large number of petitioners of Gorakhpur village, whose land was acquired by the government for setting up the plant, had moved the Punjab and Haryana high court demanding quashing of government notifications, whereby the process of acquiring around 1,500 acre land of Gorakhpur and adjoining villages of Fatehabad district was initiated.

In their petition, filed in January 2012, the farmers had also sought directions to shift the site of project towards barren or less fertile land, which is in abundance in the adjoining villages of other districts.

Contending that the plant is proposed on fertile land, which is the only source of their livelihood, villagers had submitted that the said land gives 2-3 crops per year and there is no reason why such fertile land has been selected for the plant.

Villagers have also argued that in the instant case, Haryana government has shown undue haste for acquisition of land without considering the suitability of land from Union ministry of environment and AERB and Nuclear Power Corporation.

“No public objection was invited while publishing the site selection. Farmers are protesting and the state government remained insensitive despite death of three protesting farmers in the past one year,” the petition had alleged.

During the hearing of the petition, it also emerged that a large number of petitioners had accepted compensation amount from the state government against acquisition of their land.

The Nuclear Power Corporation of India Ltd (NPCIL) is expected to start construction work of the project in August this year.

 

Kudankulam N-plant: Safety norms gains primacy over commissioning deadline


, TNN | May 16, 2013

Kudankulam N-plant: Safety norms gains primacy over commissioning deadline
Last week, the Supreme Court cleared the power plant, paving the way for early commissioning. Originally, the plant was scheduled to be commissioned in 2007.
NEW DELHI: Regardless of the recent promise made by Prime Minister Manmohan Singh to his Russian counterpart Vladimir Putin on the sidelines of the BRICS summit in Durban about the early commissioning of the Kudankulam nuclear power plant (KKNPP), the government has instructed theAtomic Energy Regulatory Board (AERB) that safety reviews of KKNPP should be run with a “fine-toothed comb” without being pressured by commissioning deadline. In fact, the government had recently invited the Operational Safety Review Team of the IAEA to do an independent safety assessment of other Indian reactors, particularly RAPS (in Rajasthan).Last week, the Supreme Court cleared the power plant, paving the way for early commissioning. Originally, the plant was scheduled to be commissioned in 2007.A whole new set of safety checks were conducted by the AERB after four valves that came from a Russian supplier were found to be “deficient”.Stung by a series of popular protests about safety issues in Kudankulam, which has inspired protests by a large number of NGOs, the government is keen that no stone is left unturned. If this means the Russians are less than pleased, sources said, so be it. They added that some of the supplies from Russian companies have been found to be below par.

NPCIL has that the commissioning of KKNPP would now happen only in June, after another set of checks are carried out. The company said the physical progress of the plant was 99.6% complete.

This week a group of 60 leading scientists wrote a letter to the PM, and chief ministers of Tamil Nadu and Kerala asking for more stringent safety checks of the KKNPP. They have sought “renewed study” of safety issues by an independent panel of experts. The scientists — most of them serving in state-run institutions — have expressed doubts, “particularly with reference to possible sub-standard components” used in the plant.

These are not scientists advocating against nuclear energy, but concerned about safety issues. “These safety concerns are compounded by the fact that Russian authorities arrested Sergei Shutov, procurement director of Zio-Podolsk, on corruption charges for having sourced cheaper sub-standard steel for manufacturing components that were used in Russian nuclear installations in Bulgaria, Iran, China and India,” they wrote in the letter, The arrest of Shutov, they cited, led to several complaints of sub-standard components and follow-up investigations in both Bulgaria and China.

While the AERB gave an in-principle clearance for fuel loading of the plant in April, hopes that it would be commissioned by May were dashed after faulty valves made news. In an effort to quell the protests and spiralling negative perception about the power plant, the government has been on an information overdrive to educate and be transparent. This week, minister of state V Narayanasamy said, “All nuclear power projects undergo an elaborate in-depth safety review during the consenting stages, like siting, construction, commissioning, etc. After satisfactory review during project stage, AERB issues operating licence to an NPP for a period of up to five years.”

Last week, responding to a question in Parliament, government assured that components supplied to KKNPP are “tested in an integrated manner during commissioning to verify their performance in accordance to design performance criteria. Any shortfall noticed in performance is addressed/corrected as a part of the commissioning programme”

 

Koodankulam Nuclear Power Plant – From Supreme Court to People’s Court?


M.G.Devasahayam

M G DevasahayamShri M. G. Devasahayam is a former IAS and Managing Trustee, Citizens Alliance for Sustainable Living, Chennai

He is the Convener of the PMANE Expert Group on Koodankulam.

Shri Devasahayam can be reached atdeva1940@gmail.com

Supreme Court Judgment–The Essence

On 6th May 2013, Supreme Court delivered the much awaited judgment on the Koodunkulam Nuclear Power Plant (KKNPP) arising out of SLP (C) 27335/2012 that had been reserved since first week of December 2012. The penultimate para (229) of the judgment reads thus: “Before proceeding to issue certain directions, it is required to be stated that the appellant, by this Public Interest Litigation, has, in a way, invoked and aroused the conscience/concern of the court to such an issue. True it is, the prayer is for the total closure of the plant and the Court has not acceded to the said prayer but his noble effort is appreciated to put forth the grievance of the local people and the necessity of adequate safety measures as is perceived. When such cause comes up before this Court, it is the bounden duty to remind the authorities “Be alert, remain always alert and duty calls you to nurture constant and sustained vigilance and nation warns you not to be complacent and get into a mild slumber”. The Atomic Energy Regulatory Board (AERB) as the regulatory authority and the MoEF are obliged to perform their duty that safety measures are adequately taken before the plant commences its operation. That is the trust of the people in the authorities which they can ill afford to betray, and it shall not be an exaggeration to state that safety in a case of this nature in any one’s hand has to be placed on the pedestal of “Constitutional Trust”.

After placing public safety on the pedestal of “Constitutional Trust”, Supreme Court has issued 15 directions for compliance by nuclear establishment and other regulators for strict compliance before commissioning of the plant. From the language, tone and tenor these conditions appear to be non-negotiable.

Response from Nuclear Establishment

Nuclear Power Corporation of India Ltd (NPCIL) response to the judgment was typical of the nuclear establishment’s vulgar hurry to impose the unsafe KKNPP on the struggling people: “With the Supreme Court giving the green signal, the first reactor of the Kudankulam Nuclear Power Project is likely to go critical anytime between May 13 and 20. Top sources in the NPCIL told ‘The Hindu’ that a team of Automic Energy Regulatory Board experts are going through the results of the test conducted a few days ago and holding discussions on the results with the NPCIL technocrats. The AERB’s governing body, expected to meet before this weekend is likely to take a final decision on giving the nod for criticality immediately”

As for RK Sinha, Chairman of the Atomic Energy Commission (AEC) it was a great relief and he said so: ‘I humbly welcome the judgment of the court, it should lay to rest all perceived doubts about the Kudankulam atomic reactor. The reactor is at an advanced stage of commissioning and criticality or the start of the nuclear chain reaction in the plant should happen soon.’

Legal Notice

It looks as if nuclear establishment had not read the judgment carefully. If they had done so their response would have been different. And they had to be reminded of it the hard way-through a legal Notice which reads as under:

“As you are aware, the Supreme Court has given several directions to be complied with before the commissioning of KKNPP including the following two directions:

1. The plant should not be made operational unless AERB, NPCIL, DAE accord final clearance for commissioning of the plant ensuring the quality of various components and systems because their reliability is of vital importance…….

15. The AERB, NPCIL, Ministry of Environment & Forests (MoEF) and Tamil Nadu Pollution Control Board (TNPCB) would oversee each and every aspect of the matter, including the safety of the plant, impact on environment, quality of various components and systems in the plant before commissioning of the plant. A report to that effect be filed before this Court before commissioning of the plant.

The above directions of the Supreme Court are categorical. These directions need no interpretation whatsoever. As per these directions, Kudankulam Nuclear Power Project cannot be commissioned as it stands now. When clearance was granted by you (AERB) for initial fuel loading (IFL) and first approach to criticality (FAC) of Unit.I of Kudankulam Nuclear Power Project on August 10, 2012 the same was challenged before the Madras High Court by my client. The said clearance was ultimately tested by the Supreme Court in Civil Appeal No. 4440 of 2013 and batch matters. Having considered all aspects of the matter, the Supreme Court has now given a direction to you (AERB & NPCIL) and the Department of Atomic Energy not to make the KKNPP operational until a fresh review of the quality of various components and systems of the KKNPP is undertaken. The Supreme Court has further given a direction to you (AERB & NPCIL) and Ministry of Environment & Forest of the Government of India and the Tamil Nadu Pollution Control Board to oversee each and every aspect of the matter, including the safety of the plant, impact on environment, quality of various components and systems in the plant and after fulfilling this task file a report in the Supreme Court before commissioning of the plant. These directions have not yet been complied with by you (AERB & NPCIL) or by the Government of India or by the Tamil Nadu Pollution Control Board.

It appears that after the judgment of the Supreme Court you have not even commenced a fresh review of the ‘quality of various components and systems in the plants’. Without even attempting to comply with the directions of the Supreme Court, NPCIL is making a statement to the press that the KKNPP is likely to go critical any time between May 13 and 20.

Kindly take notice that any such assertion on the part of NPCIL or AERB as reported in The Hindu dated 7 May 2013 would amount to contempt of the Supreme Court, since no report as directed by the Supreme Court in direction No.15 has so far been submitted to the Supreme Court.”

 

The Flaws

While this could bring some succour to the struggling farmer-fisher folk, Supreme Court judgment nevertheless suffer from several flaws:

  1. While the Special Leave Petition starts with characterising nuclear power as “the most dangerous means of producing energy with a serious potential for catastrophic accidents causing severe damage to life and property, with cost of reparation running into lakhs of crores of rupees”, the court nonchalantly and without appropriate due diligence declares that “nuclear energy…is a clean, safe, reliable and competitive energy source”. This assertion is debatable, disputable and defeats the very purpose for which the petitioners appealed to the highest court of law.
  2. On the issue DGR (Deep Geologic Repository) for radioactive nuclear waste, which is a critical issue concerning public safety, the court has been very casual: “NPCIL does not seem to have a long term plan, other than, stating and hoping that in the near future, it would establish a DGR (Deep Geologic Repository)”. Its directive that “DGR has to be set up at the earliest” does not specify a date nor make it a necessary condition before NPCIL embarks on new nuclear reactor construction. This is clear pandering of the nuclear establishment.
  3. Safety concerns that remain paramount in the minds of the citizens living in the vicinity of Koodankulam have not been adequately acknowledged by the Court, which did not even see fit to mention the problems with valves that the AERB disclosed, or the news reports of corruption in supplier companies in Russia. The Court’s call to “educate the people” smacks of condescension, which is anachronistic for a democracy and inexplicable when seen in the context of this well-informed and widely-participated movement against the Koodankulam reactors.
  4. SC’s uncritical reliance on the opinions of the nuclear establishment and its complete disregard of the absence of public trust in the regulatory agency is a serious problem with the judgment. It quotes extensively from AERB documents, especially safety codes, yet overlooks the fact that AERB and NPCIL do not often follow their own safety rules. The most pertinent example is that of Koodankulam itself, when AERB allowed the loading of fuel into the reactors even though NPCIL had not complied with its safety recommendations following the Fukushima nuclear accidents.
  5. The Court did not even acknowledge, let alone examine, the questions surrounding the independence and effectiveness of the AERB, and instead claimed that the AERB has been “regulating the nuclear and radiation facilities in the country very effectively”. Last year, the Comptroller and Auditor General (CAG) pointed out that AERB “continued to be…an authority subordinate to the central government”, putting a big question mark over its independence as a regulator. Its actions in the case of Koodankulam, unfortunately, do not enhance the credibility of the AERB. The Court claims that the AERB “has, over the years, issued a large number of codes, standards and guides”, while the CAG pointed out that the AERB had failed to prepare “a radiation safety policy even after three decades of its existence”.
  6. The court does not seem to have properly considered the prayers contained in the SLP. While the petitioner had asked for commissioning the plant after ensuring all safety & environmental requirements court has said that the petitioner wanted “total closure of the plant and we have not conceded to the said prayer”.

Not addressing corruption and sub-standard machinery issues

Another disturbing aspect of the judgment is the question as to why did SC ignore the IA filed on 23 April (two weeks before the judgment) clearly bringing to the notice of the Supreme Court the supply of sub-standard equipment and materials by ZiO Podolsk, a Russian public sector machine works company, to the Koodankulam plant, and how Unit 2 of the Leningrad nuclear power plant using similar materials supplied by the same company collapsed on 17 July 2011, leading to the arrest and prosecution of Sergei Shutov, procurement director of ZiO Podolsk, by a Federal court in Russia. All other scams/scandals like 2G Spectrum, Commonwealth Games, Coalgate etc came out and are under serious investigation because of exposures by CAG followed by activism and advocacy by civil society with legal luminaries in the forefront. Courts had not been forewarned in these scams, but when these came before the SC it took very serious notice and is pursuing these with vigour by upbraiding the government and constituting SIT etc. What happened in the Coalgate case is an apt example. But in the KKNPP case it is just the opposite. SC was forewarned about the scam, sub-standard material and corruption and criminal action in Russia against supplier company weeks before the judgment was issued and was ‘mentioned’ in open court. The least SC could have done was to ask for independent investigation in to these ‘life-threatening’ allegations and satisfied itself before issuing final orders.

On this aspect of SC judgment Dr. A. Gopalakrishnan, former Chairman, AERB has a slightly different take. This is what he has to say: “As per Directions No: 15 given in the SC Judgment, NPCIL, AERB, MoEF and TNPCB are to be jointly involved in all  aspects  of  certifying  this  reactor as safe. Of  these three  organizations (AERB, TNPCB, MoEF) are Regulatory Agencies, and NPCIL is the promoter  and  it will  have  to  serve  as  the main supplier of  inspection data and other compliance information to the other three for  review . Without  solely  resting their confidence & trust  in the  two  DAE  institutions (AERB & NPCIL) , the Supreme Court  has intentionally broadened the jury to include two additional government  regulators  who are not connected with the DAE. This I see as the impact of our last affidavit (IA on 23 April) on Zio-Podolsk corruption and supply of substandard components & equipment from  Russia. We have to make best use of this opportunity”.

This matter however has been taken care of in a complaint filed with the CBI and a writ filed in the Madras High Court for directing the CBI to conduct expeditious investigation into corruption and supply of sub-standard equipment.

Future Imperatives

Dr. EAS Sarma, former Secretary to Government of India, Ministry of Power has created a matrix for making the ‘best use’ of the 15 directions and other observations made in the SC judgment. It is presented below with some of my inputs:

 

Para Direction & Action points Compliance imperative before commissioning
230.1 The plant should not be made operational unless AERB, NPCIL, DAE accord final clearance for commissioning of the plant ensuring the quality of various components and systems because their reliability is of vital importance. Final clearance and the process adopted should be placed in the public domain as required under Section 4 of RTI Act, 2005.
230.2 MoEF should oversee and monitor whether the NPCIL iscomplying with the conditions laid down, while granting

clearance vide its communication dated 23.9.2008 under the provisions of EIA Notification of 2006, so also the conditions laid down in the environmental clearance granted by the MoEF vide its communication dated 31.12.2009. AERB and MoEF will see that all the conditions stipulated by them are duly complied with before the plant is made operational.

MOEF should place the monitoringreports in the public domain as required under Section 4 of RTI Act, 2005.
230.3 Maintaining safety is an ongoing process not only at thedesign level, but also during the operation for the nuclear

plant. Safeguarding NPP, radioactive materials, ensuring

physical security of the NSF are of paramount importance.

NPCIL, AERB, the regulatory authority, should maintain

constant vigil and make periodical inspection of the plant

at least once in three months and if any defect is noticed,

the same has to be rectified forthwith.

NPCIL, AERB should place the periodic reports in public domain as required under Section 4 of RTI Act, 2005.
230.4 NPCIL shall send periodical reports to AERB and the AERB shall take prompt action on those reports, if any fallacy is noticed in the reports. The reports should be available for the public as required under Section 4 of RTI Act, 2005.
230.5 SNF generated needs to be managed in a safe manner toensure protection of human health and environment from

the undue effect of ionizing radiation now and future, for

which sufficient surveillance and monitoring programme

have to be evolved and implemented.

 

Copy of the surveillance and monitoringreports should be available in public domain as required under Section 4 of RTI Act, 2005.
230.6 AERB should periodically review the design-safety aspectsof AFR feasibly at KKNPP so that there will be no adverse

impact on the environment due to such storage which

may also allay the fears and apprehensions expressed by

the people.

The reports should be available in public domain as required under Section 4 of RTI Act, 2005.
230.7 DGR has to be set up at the earliest so that SNF could betransported from the nuclear plant to DGR. NPCIL says

the same would be done within a period of five years.

Effective steps should be taken by the Union of India,

NPCIL, AERB, AEC, DAE etc. to have a permanent DGR at the earliest so that apprehension voiced by the people of

keeping the NSF at the site of Kudankulam NPP could be

dispelled.

The periodic progress reports should be available in public domain as required under Section 4 of RTI Act, 2005.
230.8 NPCIL should ensure that the radioactive discharges to theenvironmental aquatic atmosphere and terrestrial route

shall not cross the limits prescribed by the Regulatory

Body.

The monitored data should be available in public domain as required under Section 4 of RTI Act, 2005.
230.9 The Union of India, AERB and NPCIL should take steps atthe earliest to comply with rest of the seventeen

recommendations, within the time stipulated in the

affidavit filed by the NPCIL on 3.12.2012.

The Apex Court, in para 189, has cautioned AERB, NPCIL as follows.“Adequate measures have, therefore, to be taken for storage of NSF at site, and also for the physical safety of stored NSF. Of the seventeen suggested safety measures, by AERB, LWR, twelve have already been implemented and the rest, in a phased manner have to be implemented which the experts say, are meant for extra security”

The apex court, in para 228, has also emphasised as follows

 

Therefore, I am obliged to think that the delicate balance in other spheres may have some allowance but in the case of establishment of a

nuclear plant, the safety measures would not tolerate any lapse. The grammar has to be totally different. I may hasten to clarify that I have not discussed anything about the ecology and environment which has been propounded before us, but I may particularly put that the

proportionality of risk may not be “zero” regard being had to the nature’s unpredictability. All efforts are to be made to avoid any man-made disaster. Though the concept of delicate balance and the doctrine of proportionality of risk

factor gets attracted, yet the same commands the highest degree of constant alertness, for it is disaster affecting the living. The life of some cannot be sacrificed for the

purpose of the eventual larger good.”

Therefore, NPCIL is expected to lay down strict time schedules to ensure safety and the progress reports should be available in public domain as required under Section 4 of RTI Act, 2005.

230.10 SNF is not being re-processed at the site, which hasto be transported to a Re-Processing facility. Therefore,

the management and transportation of SNF be carried out

strictly by the Code of Practices laid down by the AERB,

following the norms and regulations laid down by IAEA.

The details should be placed in public domain as required under Section 4 of RTI Act, 2005.
230.11 NPCIL, AERB and State of Tamil Nadu should takeadequate steps to implement the National Disaster

Management Guidelines, 2009 and also carry out the

periodical emergency exercises on and off site, with the

support of the concerned Ministries of the Government of

India, Officials of the State Government and local

authorities.

Hon’ble Madras High Court in W.P.No.24770 of 2011 August 2012 (Para 89) observed as follows“Even though it is stated that the said exercise was done in only one village, namely Nakkaneri village, which is stated to be nearer to the KKNPP, as we are informed that nearly 30 to 40 villages are within 30 Kms radius of KKNPP, such event must take place in all villages and more importantly, apart from the officials, as stated above, the people in the area must be made to participate and an awareness programme must be made to infuse confidence in the minds of the local people that the project is for the benefit of the country and there is no need to alarm”

Since this observation has not been modified by the apex court, it should be treated as a pre-condition to commissioning of the plant. In addition, implementation of NDMA’s guidelines should also precede commissioning.

The Apex Court’s observation in para 221 (extracted below) of the judgment has importance

“The concept of disaster management cannot be allowed to remain on paper. Its procrastination itself rings the bell of peril. The

administration has to be alive to the said situation and the awakening to manage the disaster in case of an

unfortunate incident has to be founded on scientific and

sophisticated methods. Taking care of the situation of the present alone is not the solution. All concerned with the same are required to look to the future because that elevates the real concern. The danger of the future should be seriously taken note of and should not be veiled in the guise of thought for the present”.

230.12 NPCIL, in association with the District Collector,Tiruneveli should take steps to discharge NPCIL Corporate

Social Responsibilities in accordance with DPE Guidelines

and there must be effective and proper monitoring and

supervision of the various projects undertaken under CSR

to the fullest benefit of the people who are residing in and

around KKNPP.

Progress reports with the names of beneficiaries should be placed in public domain as required under section 4 of RTI Act. A special audit should be ordered to ensure proper utilisation of the funds
230.13 NPCIL and the State of Tamil Nadu, based on thecomprehensive emergency preparedness plan should

conduct training courses on site and off site administer

personnel, including the State Government officials and

other stake holders, including police, fire service, medicos,

emergency services etc.

Progress reports with the names of trainees should be placed in public domain as required under section 4 of RTI Act. A special audit should be ordered to ensure proper utilisation of the funds
230.14 Endeavour should be made to withdraw all thecriminal cases filed against the agitators so that peace

and normalcy be restored at Kudankulam and nearby

places and steps should be taken to educate the people of

the necessity of the plant which is in the largest interest of

the nation particularly the State of Tamil Nadu.

 

This should precede commissioningction taken should be placed in public domain as required under Section 4 of RTI Act
230.15 The AERB, NPCIL, MoEF and TNPCB would overseeeach and every aspect of the matter, including the safety

of the plant, impact on environment, quality of various

components and systems in the plant before

commissioning of the plant.A report to that effect be filed before this Court before commissioning of the plant.

The Report thus filed should be notified to the Petitioner for filing counter and if found ‘fake’ SC should order investigation of quality of various components and systems in the plant by an Independent Expert Group before issuing final orders.

Compliance requirement suggested for Direction #15 assumes all the more importance due to post-judgment revelations through a research study that the reactor pressure vessel (RPV) supplied to KKNPP, considered to be the heart of the reactor, could be obsolete and different from the originally promised one. This has humongous repercussions and if unchecked, has all the potential for a catastrophe in peninsular India and the island of Sri Lanka. Serious charges of corruption and suspicion of substandard material and obsolete RPV have arisen, but not addressed even by the highest court of law. God forbid, if some incident/accident happens during commissioning or after, besides human catastrophe it would devastate SC as an institution and extinguish whatever little faith people have in this bulwark of justice. Supreme Court monitored pre-commissioning is therefore a must because the Court has placed public safety on the pedestal of “Constitutional Trust” and hopefully would never countenance its betrayal by the nuclear establishment.

The Groundview

But the ‘soldiers on the ground’ have a different perception altogether. They are of the view that in order to free up Russia from supplier liability, charges of theft and abject project failure, the Indian nuclear establishment has begun to claim that the KKNPP is not a Russian turnkey project.

Following the Supreme Court’s verdict, nuclear establishment is announcing various dates to fake-commission the project and trying to protect their own self interests and save the Russians from all the embarrassing and serious charges. Instead of answering the component-related concerns, financial improprieties and liability commitments in an earnest manner, they are spreading irresponsible rumors and conjectures as they have been doing since 2005 about commissioning the KKNPP.

In fact, the KKNPP authorities do not even allow journalists anywhere near the reactors for fear of their smelling any of the fishy things that have been happening there. In an interview RS Sundar, the site director has claimed that they are facing difficulties with the media.

This is what the struggle leaders have to say: “The Indian government, Department of Atomic Energy (DAE), and the AERB do not even want to walk the extra mile of assessing the quality and safety of the components with a team of independent scientists, engineers and journalists. No one in India knows anything about the omissions and the commissions of the KKNPP, NPCIL, AERB, DAE, AEC and their Russian counterparts and suppliers. Even the Indian courts seem to accept the establishmentarian views in spite of the fact that they have laid down fifteen directions in their recent judgment. All nuclear establishment want is commissioning of the plant even if it is a fake one! So all the thefts, untested technology, unsafe components and the overall failure could be buried in radioactive contamination and inter-governmental cover up.”

So the struggling community, all ordinary citizens of India, have decided to turn to their fellow citizens and Mother Nature to protect the interests of our country and people. They have decided to come out in the open, travel to neighboring villages and organize people all over again. They have decided to fight it out to the finish and are confident that they shall overcome.

To this determination Admiral L.Ramdas has responded to the struggle coordinator Udayakumar: “We are happy to see that the spirit of “Never say Die” prevails. I am sure our prayers and hard work and commitment will not go waste. Regards and Greater strength to your elbow”. So, it is from Supreme Court to the Court of the People.

We are a Democracy and VOX POPULI is VOX DEI–‘Voice of the People is Voice of God’. But is mere voice enough? To seek assurance, ground forces should draw on the famous clarion of Alexander Solzhenitsyn: “It is infinitely difficult to begin when mere words must remove a great block of matter. But there is no other way if none of the material strength is on your side. And a shout in the mountains has been known to cause an avalanche

Just replace ‘mountain’ with ocean and ‘avalanche’ with tsunami. BRAVO.

 

PRESS RELEASE- Supreme Court Verdict on Koodankulam: A Travesty of Justice


PRESS RELEASE

Mumbai, May 15 , 2013

The Supreme Court’s verdict on Koodankulam rests on three hugely contested premises: the judges’ belief in the necessity of nuclear energy for India’s progress, their faith in the  nuclear establishment to perform its role, and the judges’ notion of the larger public interest and the apprehensions of small sections which should be subordinated to the estblishment’s plans. Not only have the judges given judicial sanctity to these contestable propositions, they  have also completely overlooked Koodankulam-specific brazen violations of the government’s own norms, raised by the petitioners.

It is unfortunate that the Court, far transgressing the actual prayers of the petition, has completely overlooked the brazen violations by the Nuclear Power Corporation of India Limited (NPCIL), the Atomic Energy Regulatory Board (AERB) and the Tamil Nadu Pollution Control Board (TNPCB) of their own norms. The petitioners has highlighted serious issues such as the recent scam in Russia involving ZiO-Podolsk’s supply of sub-standard equipments to Koodankulam, violation of the AERB’s reactor-siting norms, undermining of Environmental Impact Assessment (EIA) and Coastal Regulatory Zone (CRZ) clearances, flouting of the mandated  emergency preparedness and evacuation exercises, the AERB’s 17 post-Fukushima recommendations etc.

The DAE’s complete hegemony on nuclear expertise in India and its proximity to the country’s top political leadership has been misused by it to mislead the Supreme Court. Extensive citation of the AERB’s safety codes for Pressurised Heavy Water Reactors  (PHWRs) in the judgement whereas the Koodankulam reactors are Pressurised Water Reactors (PWRs) is a glaring example of this. The verdict also highlights the unfortunate extent to which our democratic institutions, including the judiciary, have come to unquestionably accept the growth-centric model of ‘development’ which is being contested by impoverished and marginalised sections who are bearing its brunt.

We demand that the NPCIL exercises maximum transparency and accountability in implementing the 15 guidelines issued by the Court. The Court’s order to withdraw police cases against the agitators vindicates our position that the government used undemocratic and brutal repression to silence the peaceful protests in Koodankulam.We demand that these fabricated charges be withdrawn at once.

 

issued by: The Coalition for Nuclear Disarmament and Peace (CNDP) , a  national network of various organisations along with Konkan Vinashkari Prakalp Virodhi Samiti,Madban Janhit Seva Samiti,Jaitapur Anuurja Prakalp Virodhi Samiti and various other organisations and individuals

Join us on facebook:- https://www.facebook.com/groups/109358664039/

To be updated on nuclear issues :- http://cndpindia.org/ ,  http://www.dianuke.org/,

For more information contact- Vivek Sundara (CNDP) -9821062801 /Kamayani Bali Mahabal ( CNDP)  9820749204

 

Does the Supreme Court care about Indian lives?


The reasons behind clearing the Koodankulam nuclear plant defy logic and democratic principles
SP Udayakumar

18-05-2013, Issue 20

This week, a bench of the Supreme Court (SC) cleared the commissioning of the nuclear power plant at Koodankulam, against which the residents of the area have been protesting for the last 630 days. We find this verdict to be highly unfortunate, and feel that it doesn’t take into account the value of Indian lives.

Ten days before the judgment, our supporters Poovulagin Nanbargal (friends of the earth) filed an affidavit before the Court that ZiO-Podolsk, which has supplied much of the equipment to the plant, is a discredited and corrupt company. Sergei Shutov, the procurement director of the company, was arrested in February 2012 on charges of using substandard metal in their equipment. When we filed an RTI with Nuclear Power Corporation of India Limited (NPCIL) this January, they denied having received equipment from ZiO-Podolsk, and it was only after repeated enquiries that the NPCIL was forced to admit the truth. This is a very serious matter; if anything were to go wrong, crores of lives would be lost. Yet, the SC refuses to consider this issue while announcing its verdict.

Even accepting, for the sake of argument, that this matter came to light after the Court reserved its judgment, and thus cannot be admitted, what about waste management? The Department of Atomic Energy (DAE) told the Court that the waste would be buried under the Kolar gold fields in Karnataka, but the plan was dropped after the residents protested. And that was that. The Court didn’t ask again what alternative the DAE had, and passed its judgment without settling the question. So what happens to this highly toxic waste?

As for liability, an inter-governmental agreement of 2008 holds that the Russians would not be liable in case the faulty equipment malfunctions. What a great deal! You buy whatever rubbish they give you, and you exempt them from liability. So much money has been stolen by both rich Indians and Russians, and the poor locals have to bear the brunt of the greater risk. Who is liable? Is Manmohan Singh liable? He might not be in power two months from now. Would it be the DAE? The KKNPP site director Kasinath Balaji has disappeared, and someone else is in his post. The NPCIL? SK Jain, who was the chairman, is now leading a cushy life in Tokyo as the chairman of the governing board of the World Association of Nuclear Operators. Who will be here to answer for something going wrong? We do not trust these bureaucrats and officials, and now we can’t even trust the SC. If the SC cared about Indian lives, it should have asked these questions.

But no, the Court says that a balance has to be struck between the right to life and sustainable development, that the larger public interest should prevail over minor inconveniences caused to local people. If the inconvenience is really minor, why don’t they build the plant near Parliament? The “larger public interest” it speaks of is nothing but the interests of large corporations for which poor fishermen, women and children should apparently sacrifice their lives and livelihoods.

Regardless, our struggle continues. We may not be successful in closing the plant tomorrow, or in the next few months, or few years. We are patient. We shall persevere. For we have persevered despite the government’s campaign to spread lies and libel us. They have claimed that those who oppose the Koodankulam plant are foreign stooges and that we receive money from abroad. VS Achuthanandan, the former chief minister of Kerala, opposes the plant. Did he take money from abroad? Dr A Gopalakrishnan, the former head of the Atomic Energy Regulatory Board, has written extensively against the plant. Does he do so for foreign money? Admiral (Retd) Ramdas opposes the plant. Medha Patkar is against it. So is Aruna Roy. Who paid them? Why, when such luminaries have stood up against the government’s anti-people stance, should nameless, faceless Udayakumar be singled out by the Americans for payments?

I don’t take the government’s vilification seriously, because I have nothing at stake. I am not trying to join politics, and I don’t need a certificate of approval from anybody. It’s not me anyone should be worried about, but the people of Idinthakarai, of Koothankuli, of other villages that will be affected, who have lost so much because they chose to take a stand. They have lost their incomes, they have been arrested, they have been attacked by the police. With the opening of the plant, things will only get worse.

But we persist, because we firmly believe that we are fighting for the good of our country, for which we have an enormous amount of love. India needs development, we agree, but in seeking that development, we must not undermine our natural resources, or the basic health of our people and our nutrition security. What are our priorities, after all? Half of our population lives under 20 a day, half of our population barely has any sanitation. We don’t have the basic necessities. People are dying for want of safe drinking water. Instead of addressing these issues, why does our government persist in its obsession with nuclear power, which only adds to the suffering of the poor? Yes, we need electricity, but there needs to be leadership in how we go about harnessing it. If a country like Germany can develop so much electricity from solar power, why can’t we? We have been vilified as fighting against the interests of our country. We have been called Luddites standing in the way of progress. But it must be made clear that we are not against electricity, only nuclear power. We are not against development that benefits Indians, but against that which benefits corrupt Russian companies. We want our people to live as human beings, in a State that does not compromise their safety or on the basic necessities of life.

The greatest challenge we have faced in the course of our protest is the power differential between the people and the State. We celebrate our country as the world’s largest democracy, but its people are hopelessly powerless. Nobody listens to the people. The Parliament wastes our time, energy and resources. Even to ask a question in Parliament, we must bribe MPs, and even when they ask the question, it is just a ritual. No serious debate takes place. This democracy we speak of is a sham. It works only to cheat the poor of their rights.

As told to Ajachi Chakrabarti

letters@tehelka.com

(Published in Tehelka Magazine, Volume 10 Issue 20, Dated

 

Koodankulam:A Court in the Supreme Contempt of its People


injustice

 

The Supreme Court’s verdict on Koodankulam rests on three hugely contested premises: the judges’ belief in the necessity of the nuclear energy for India’s progress, their faith in the country’s nuclear establishment to perform its role, and the judges’ notion of the larger public interest and the apprehensions of small sections which should make way for the country’s progress. Not only have the judges given judicial sanctity to these contestable propositions, but have also completely overlooked the Koodankulam-specific brazen violations of the government’s own norms, raised by the petitioners.

injusticeThe Supreme Court’s judgement on Koodankulam would go in India’s history in line with the Narmada Dam verdict and other judicial pronouncement reflecting the inability of our post-independence democratic institutions to overcome the narrowly defined confines of ‘larger public interest’, ‘development/growth’ and ‘national conscience’.

Whose interests are larger?

While the petition filed by the Chennai-based environmentalist group Poovulagin Nanbargal presented specific concerns of safety hazards and violations of the government’s own norms in implementing the project, India’s growth and the assumed indispensability of nuclear energy for it is a recurring rationale in the Supreme Court’s final verdict. The judges have gone beyond the scope of the prayer and have extolled nuclear energy as essential for India’s growth, terming the ‘fears’ of people as misplaced. The judgement goes on to prescribe that ‘minor inconveniences’ must be tolerated in the larger interest of the nation.

DOCUMENTS:

TEXT of the Supreme Court’s Judgement on Koodankulam

Koodankulam Scam: TEXT of the Petition Filed in the Supreme Court by Adv. Prashant Bhushan

Special Leave Petition on Koodankulam filed in Supreme Court

Writ Petition on Nuclear Liability for Koodankulam Filed in the Supreme Court of India

People’s Movement is Emotional fear, Nuclear Establishment has the Expertise

The second paragraph of the judgement itself calls the people’s massive agitation in Koodankulam an “emotional reaction” to the setting up of the reactor. It almost mocks the people’s concern saying the “fears and unrest” might not have been thought of by Enrico Fermi who set up the first nuclear power plant. Since then, the judgement says, people have reacted emotionally when every new reactor is commissioned. The judgement goes on to add that the people’s concern was mooted even the constituent assembly when the Constitution was being drafted. Does this imply that nuclear energy in India should be regarded a fait accompli?

The judgement accepts the establishment’s narrative on nuclear energy in India unquestioningly.

  • The judgement extols the Atomic Energy Commission (AEC) as the repository of final authority on everything nuclear and the Atomic Energy Regulatory Board (AERB) as a competent regulator, glossing over its dependence on the AEC for funds and human resources and its being obliged to report to the AEC whose activities it is essentially mandated to regulate.
  • The verdict also reposes complete faith in the national policy on nuclear energy and the existing framework to control and regulate all radioactivity-related activities in India.
  • Under the title ‘National Policy’ (page 9) the judges narrate the evolution of India’s 20 nuclear power stations built over last four decades producing 4780 MWs today with a rare clinical coldness, without questioning the nuclear establishment’s claims and its performances in the same period, while under the same title on page 10, it mentions that renewable sources provide “small share” of our total electricity – 15%, which is actually 6 times more than the share of nuclear energy. 
  • In its overview of the global status of nuclear energy, the rapid downward trend of the industry post-Fukushima doesn’t find a mention – France produces 74.6%, US has 104 reactors, world had 439 reactors in 2007 producing 13-14% of total energy. The reality is, nuclear power produced just 11% in In 2011 and the downward trend is expected to continue due to larger number of reactors ageing and lesser numbers being built today.
  • It doesn’t even question the NPCIL’s claims of producing 20,000 MW by the year 2020 and 63,000 MW by 2030.
  • Transgressing the scope of the petition, the judges have mentioned that “one of the reasons for preferring nuclear energy as an alternative source of energy is that it is a clean, safe, reliable and competitive energy source which can replace a significance of the fossil fuel like coal, oil, gas etc.” The judges have not bothered to see that each of these adjectives have been questioned and have led to review of national policies, including in France where a national energy transformation law is underway.

As the questions raised in the petition involved technical problems plaguing the Koodankulam project, the Court consulted the government’s experts – officials from the Nuclear Power Corporation of India Limited (NPCIL) and the Atomic Energy Regulatory Board (AERB). Unfortunately, no independent institutionalised expertise on nuclear issues exists in India outside the confines of the Department of Atomic Energy.  This led to a situation in which the Judges have no option than to believe the same official experts against whose refusal to acknowledge the risks was the petition filed. While this made the entire proceeding lop-sided in the first place, there was still scope for the judges to look into the glaring violations and specific risks in Koodakulam which do not fall strictly under nuclear expert issues.

The crucial issues of supply of sub-standard equipments by ZiO-Podolsk, violation of Coastal Regulatory Zone stipulations and Environmental Impact Assessment norms, lack of clarity on the crucial issue of spent fuel storage, non-compliance with proper mock evacuation drill required by the AERB norms, much larger population in the vicinity than stipulated etc. have either been glossed over or have been legalized post-facto.

Court validating a political deal?

The judgement mentions India’s civil nuclear agreement with the US in 2005 and then with France and UK in 2008 and 2010, and explains them as the govt’s effort give effect to the “National Policy for development” for which “India has entered into various bilateral treaties and arrangements with countries which have considerable expertise and experience”. It is a well known fact that the nuclear deal came from the US side and the energy justification was a later concoction to justify it. The integrated energy policy of 2006 came one year after the Indo-US nuclear deal. In fact, it was the nuclear establishment in India which was the first one to get surprised with the news of Indo-US nuclear deal in 2005. The deal was essentially about the US manoeuvring internationals institutions norms of the  NSG and the IAEA to legitimise India’s nuclear weapons and ensure its entry into global international commerce. India’s compulsory purchase of the French, American and Russian reactors was a price it paid to achieve this. Former AEC Chairman Anil kakodkar himself has admitted in the past that importing foreign reactors, with an embarrassingly low liability cap,  had to do with accommodating these countries’ interests.

 Nuclear Energy and National Policy

After enthusiastically elaborating India’s national policy on nuclear energy, the judges say, “it is not for Courts to determine whether a particular policy or a particular decision taken in fulfilment of a policy, is fair” (page 13). Precisely. The petition before the court nowhere sought to discuss the rationale or desirability of the nuclear policy, if at all India has one. The petition raised concrete questions about safety norms and their violations. Then why the judges have went on to declare nuclear energy is green, clean and essential for India’s development? The judges quote an old case in Lodon to undermine that its “only duty is to expand the language of the Act in accordance with the settled rules of construction”, and hence “we cannot sit in judgment over the decision…for setting up of KKNPP in Kudankulam in view of the Indo-Russia agreement”. Fine, but what about ensuring that the inter-governmental agreement between India and Russia is made public and the liability provisions within it be made compliant to the law of the land?

After the aforementioned introductory part, the SC verdict has two parts – the first deals with safety and security of NPP, International COnventiions and Treaties, KKNPP Project, NSF and its management and transportation, DGR, Civil Liabilities, DMA, CSA and other related issues. Part II deals with environmental issues, CRZ, desalination plant, impact of radiation on eco-system, expert opinions, etc.

In part I, the verdict seeks to find out whether the project has adequate safety measures. In doing so, it starts with elaborating the Safety Codes of the AERB (in 12 full pages), without questioning its institutional autonomy or making mention of the CAG’s report on the AERB in which it strips down the myth of AERB’s independence and its efficacy. Details of India’s international obligations and its adherence with IAEA safety norms, based on the AERB’s submission, take several pages more.

IAEA’s 2008 report emphasizing tripling of electricity supply by 2050 is highlighted by the judges. The IAEA’s contested claim of nuclear energy being a low-carbon electricity is adopted unquestioningly.

The verdict reposes its complete faith in “the safety and security code of practices laid down by the AERB, the IAEA and its supports so as to allay the fears expressed from various quarters on the safety and security of KKNPP”

The judges mention PUCL vs Union of India and others case of 2004, where the court upheld that the AEC deals with a sensitive subject. The veil of secrecy remains intact in 2013 even if the civilian and military nuclear facilities are separated as per the Indo-US nuclear deal.

Safety Issues:

Reading the Supreme Court verdict’s sections on Koodankulam’s safety is not much different than reading AERB’s or NPCIL’s stated policies on nuclear safety. Elaborate claims of safety standards and practices, but very little about whether these guidelines sufficiently address the specific questions raised by the protests, even less on how efficient and democratic these procedures are.

In the section under part-II titled “KKNPP  Project” the judges have looked into site selection procedures and site-specific vulnerabilities of Koodankulam. The judges come out convinced that Koodankulam is totally safe for the reactor project – having absolutely no potential of earthquake, Tsunami or other geological disturbances. The evidences presented by the petitioners about the area being geologically unstable and having a history of earthquakes, volcanism and karst have gone completely unheard.

Much attention has been given to the questions of safely storing Spent Nuclear Fuel (SNF) and finding a Deep Geological Repository (DGR) for KKNPP. These are generic issues plaguing nuclear reactors everywhere and globally the nuclear industry has been struggling to find the answers for several decades. Not surprisingly, there are ready-made and extremely tentative solutions: the NPCIL has agreed to find a repository to store nuclear waste and has given details of its long-term pursuits in this direction, and it has assured the court to safely story the SNF. The AERB’s code of “Management of Radioactive Waste” has been discussed at length, to be found sufficient to address the problem. Typically, Indian nuclear establishment does not acknowledge nuclear waste as waste, because it claims it will reprocess most of it for the second phase of its 3-phase  nuclear programme, to which even the judges have shown admiration. Lost of course is the fact that reprocessing leads to more harmful and long-term wastes and India’s phased nuclear program has been too far from becoming a reality. The judges note : “the experts feel that setting up of a DGR is not much of a technological challenge…but more of a socio-political issue”. The massive  disapproval of proposed waste repositories in the US and elsewhere was based on independent expert opinion is lost again. The verdict mentions a proposed DGR in the abandoned Kolar mines of Karnataka. Of course on this and other several important issues, the NPCIL retracting publicly from its position taken in affidavits filed in the SC had its own trail over last 6 months.

The judges have noted that the Koodankulam reactor has its Spent Fuel Pool inside the primary containment, with a capacity to store fuel equivalent to 7 years of full power operation of  the reactor. That the presence of SFP close to the reactor core complicated the accident in Fukushima and is a concern even today in Japan finds no mention, of course.

Fukushima never happened !

While the judges mention the post-Fukushima safety review ordered by the Prime Minister, they have failed to take into account the critiques of the whole process and the serious risks of relying on such an internal safety review without any independent supervision or assessment. On the 17 Koodankulam-specific recommendations, the court is assured by the AERB that the NPCIL will implement them satisfactorily. In the subsequent paragraphs, the verdict rhymes the nuclear establishment’s lullaby on radiation: We are exposed to radiation in our daily lives, cosmic radiation, radiation from earth’s crust, air travel, X0ray, CT-Scan, angiography, angioplasty etc etc.

In the section titled ‘Response to People’s Resistance’, the Supreme Court gives a sanitized, government version of the dialogue with people. It makes no mention of the fact that the 15-member expert committee appointed by the government did not even bother to meet the protesting people in Idinthakarai, declined from sharing essential safety-related documents with people and completely failed to address the questions raised by the movement. While this sham of a dialogue was on, the state government kept on piling false police charges, the local congress goons kept beating the protesters, the local media kept provoking against the movement leaders and none other than the PM indulged in maligning the people’s genuine struggle. The judgement quotes the government experts group’s conclusion at length and feels satisfied. It also takes no notice that the fact that the Ex-AEC Chief’s appointment as the head of expert committee constituted by the Tamil Nadu State Government subsequently reflected a seriosu conflict of interests.

Under the heading ‘Civil Liability for Nuclear Damage’, the judges in principle agree to the importance of strict liability in nuclear sector, but fail to address the Koodankulam-specific problem of opacity on liability issue. The Russian officials have been claiming they have an exemption from liability under the Inter-Governmental Agreement (IGA)

Discussion on Disaster Management Plan (DMP), the SC verdict elaborates about the guidelines of the National Disaster Management Authority (NDMA) on radiological emergencies and has pressed for better coordination between the NDMA, the DAE, and the state administration to ensure swift evacuation and management in case of a disaster. Much emphasis has been given on the need to spread awareness among the people about nuclear accidents, however, the brazen violation and bluffing by the NPCIL on disaster management receives no attention.

Although the Supreme Court quotes AERB’s norms on population near a reactor sites and specifically mentions that no public habitation should be there within 1.5 km radius of the reactor, it has failed to take into account the Tsunami Colony in Koodankulam where more than 2500 people reside at a distance of just 700- metres from the reactor. Also, the judges have held that the emergency preparedness plan (EPP) for KKNPP is adequate for around 24000 people in the 5 km radius called ‘sterilised zone’ while the norms stipulate not more than 20000 people. The catch here is, the even the 24000 figure used by the SC is taken from 2001 census, not the 2011 census!

The judges admit the importance of the mock-drills and off-site emergency exercises, but strangely caution that ‘such mock-drills are conducted to educate the public not to scare them away, but make them understand that the project is part of the national policy, participatory in nature, and hence we cannot remain as a nuclear-isolated nation’. This would only ensure that the nuclear establishment remains insulated from public scrutiny. The judges’ faith in the affidavit filed by the district administration on off-site emergency exercises flies in the face of reality.

In the last paragraphs of part-I, the Supreme Court judges have iterated their faith in NPCIL’s promise to fulfill its corporate social responsibility (CSR) – millions of rupees allotted for building schools, hospitals, roads and so on. From Tarapur to Rawatbhata to nearby Kalpakkam, local people have seen the realities of such promises.

The second part of the verdict, focused on environmental impacts, again starts with the need to look at environmental issues in the perspective of indispensability of nuclear power in the ‘national policy’ – nuclear energy has a unique position in the emerging economics in India, it is a viable source of energy and it is necessary to increase country’s economic growth !

The judgement in this part dwells elaborately upon the arguments presented by the both sides, but only to concur with the government that Koodankulam project does not violate environmental impact assessment guidelines as the project was notified in 1988, prior to enactment of EIA requirements in 1994! The flimsy affidavits filed by the NPCIL and the MoEF have found better audience with the Supreme Court judges. The court has elaborated upon the rather general and very lenient attempt of taking of environmental impacts in Koodankulam as per a letter written by the then Prime Minister, quotes the 1989 memorandum of the MoEF, the 1989 stipulations by the AERB for clearance, and finally with the MoEF’s letter dated 6 September 2001 in which it legalised the violations in the wake of 377.30 crores already spent on the project, feels confident that the environmental impacts have been taken care of and no violation of EIA stipulations have happened. In case of Coastal Regulatory zone (CRZ) clearance, it again validates the 1994 exemption given to the Koodankulam project.

The EIA reports for the proposed 4 other reactors in Koodankulam have used the EIA studies for Koodankulam 1 and 2 as base-line, which were prepared without a public hearing. Supreme Courts doesn’t find it worthy of objection.

Modifying the initial plan to take water from two nearby dams, construction of a desalination plant was started in 2006 in Koodankuiam. The petitioners had pointed out that the desalination unit would have its own hazardous environmental impacts and will also add to the overall pollution and hence had demanded a fresh EIA clearance. The court has said that desalination units are not listed under the 1994 EIA stipulations, so absence of such an EIA in Koodankulam is not a violation. Of course, the cumulative impacts also do not need any re-assessment then!

Similarly, the Supreme Court has brushed aside significant objections on CRZ clearance and post-factto legalization by TNPCB of the increased temperature of affluent water in Koodankulam. Under the heading ‘Sustainable Development and Impact on the Eco-System’, the verdict quotes elaborately from the Rolay Commission on Environment Pollution (UK, 1971), Stockholm Conference (1972), UNGA’s World Charter for Nature (1982), Rio Summit (1992), the UN MIllenium Declaration of 2000, UN Conference on Sustainable Development (June 2012) and so on, but only to conclude that “we have already found on facts that the KKNPP has been set up and is made functional on the touchstone of sustainable development and its impact on ecology has been taken care of following all national and international environmental principles” !

Larger Public Interests

Then the judges take it upon themselves to decide whether the claims of “smaller violations” of nearby population’s right to life under Article 21 of the Constitution should take precedence over production of energy, which is “of extreme importance for the economic growth of our country..to alleviate poverty, generate employment etc.” The judgement looks into various earlier cases of objections to ‘development’ projects on environmental and right to life grounds, and concludes that a balance between “economic scientific benefits” and “minor radiological detriments” has to be found. The pre-conceived notions of ‘development’ take over the judicial rigour and objectivity and in their hurry, the judges have done a grammatical faux pas: “Larger public interest of the community should give way to individual apprehension of violation of human rights and right to life guaranteed under Article 21″! We can over look the grammatical blunder of our judges, but what about terming the massive protests by thousands of people in Koodankulam, run for over 25 years in a thoroughly peaceful manner, as ‘individual apprehension’? Who is the ‘larger community’? Do the interests of the farmers, fishermen and poor people of India do not form the ‘larger public interest’?

The judges have gone ahead to claim that apprehensions of far reaching consequences of radioactive effects has “no basis”! The say: “Nobody on the earth can predict what would happen in future and to a larger extent we have to leave it to the destiny….Apprehension is something we anticipate with anxiety or fear, a fearful anticipation, which may vary from person to person.” The Court goes by the “expert opinions” of MoEF, EAC, TNPCB, Report of IOM, Report of Engineers India Limited, NEERI’s EIA etc and concludes that all expert bodies are unanimous that in their opinion KKNPP has fully satisfied all safety norms.

Justice Dipak Misra in his prologue emphasizes the need to “march ahead with life allaying all apprehensions with a scientific mindset accepting the nature’s unpredictability to survive on the planet earth on the bedrock of the doctrine – survival of the fittest”. He again goes on to describe how elaborate the DAE’s guidelines on nuclear safety are, and concludes that ‘all possible measures have been taken to avoid any kind of calamity’. He goes on to quote extensively from the IAEA’s 1994 Convention on Nuclear Safety and the Joint Convention on the Safety of Spent FUel Management and on the Safety of Radioactive Waste Management 1997, to which India is not even a signatory, to appreciate the “world wide concern for public safety”. He again quotes in extenso from the AERB’s post-Fukushima Safety Review of KKNPP. However, an unquestioned faith in the nuclear establishment about adequacy of these recommendations and the establishment’s sincerity to implement leads to plain judicial reassurances.

Justice Misra looks into proportionality of safety vis-a-vis the necessity of nuclear energy development. While accepting the need for ensuring safety for present and future generations, he holds that ‘generation of nuclear energy is a necessity in a progressive modern state’ and ‘promotion of development and protection of the environment have to be harmonized’. Besides other cases, Justice Misra cites the Narmada case and quotes that “In a democracy, welfare of the people at large, and not merely of a small section of the society, has tobe the concern of a responsible Government.”

In the final judicial directions, the judges have asked the NPCIL to file a report before the Supreme Court before the final commissioning, certifying that each and every aspect of safety including environmental impacts, have been taken care of. For the periodical safety maintenance and reviews, safety of the spent nuclear fuel during transport, radioactive discharge to the atmosphere, compliance with the 17 post-Fukushima recommendations, and adherence to the NDMA guidelines, the court has directed the NPCIL, AERB, MoEF, TNPCB and other concerned bodies ensure strict compliance, but has essentially reposed faith in their efficacy and sincerity. The Supreme Court has ordered that a Deep Geological Repository should be set up at the earliest so that SNF can be transported from the nuclear plant to the DGR.

Withdraw Criminal Cases Against Protesters: The Supreme Court has directed to withdraw al criminal cases filed against the agitators in Koodankulam and to restore normalcy and peace.

The Supreme Court’s verdict rests on three major premises: the judges’ belief in the necessity of the nuclear energy for India’s progress, their faith in the country’s nuclear establishment to perform this role, and the judges’ notion of the larger public interest and the apprehensions of small sections which should make way for the country’s progress. All three of these are immensely contested propositions. But not only have the judges given judicial sanctity to these contestable claims, but have also completely overlooked the Koodankulam-specific brazen violations of the government’s own norms, raised by the petitioners.

In retrospect, the struggling people of India would find approaching to the Supreme Court in such matters pointless, and counter-productive, as the courts themselves are part of the system which has failed to address the widening gap between the aspirations and lives of the deprived masses and the mainstream notions of ‘larger public interest’. Prayers before the judiciary on such matters ends up legitimising the same ‘experts’ and disastrous notions of progress that the people have been fighting against.

 

Chain Fencing work by NPCIL begins at proposed Nuclear plant in Fatehabad, Haryana


Work on fencing starts at region’s first N-plant

Awaiting final environment impact assessment by the expert appraisal committee (EAC) of the Centre, the ambitious Fathebad nuclear plant in Gorakhpur is set to roll.

The Nuclear Power Corporation of India Ltd (NPCIL) — nodal agency for the project — has already started work on chain fencing the property that spans 1,313 acre where the plant will be situated and 187 acres where the residential colony will come up. The EAC, which has already taken stock of the ground level situation at the site, has forwarded certain queries on land compensation award and flooding of the area to the plant officials.

Over 10 senior officials of the plant have shifted their base to the site in Fatehabad. The plant will have two residential colonies — one for its employees and another for Central Industrial Security Force (CISF) personnel.

Once the Ministry of Environment and Forest gives green signal to the project, the project will go to the Atomic Energy Regulatory Board for final approval.

T R Arora, Project Director of the plant, said: “We are ready with details to answer the queries. All formalities are now complete. The land is in our possession and is currently being chain-fenced. Once the MoEF clears the project in another two months or so, we will move for final clearance by the Atomic Energy Regulatory Board. Most probably, will be able to start construction by year end.”

According to the policy, the home state is eligible to get 50 per cent share from the plant. This will majorly help the Haryana government, which is struggling to meet power demand of its consumers. The state that lacks enough own resources of power generation, has to buy power from private players during peak season.

Haryana is also vying to get its share in the plant on the basis of development indicators. If the NPCIL agreed to the demand, then the government will get another 5.6 per cent of power share from the plant. However, the NPCIL authorities are non-committal over the state’s claim on extra share.

Meanwhile, the state has given compensation to farmers whose land has been acquired for the project at the collector rate of Rs 20 lakh per acre besides a solatium at 30 per cent and interest at 12 per cent per annum under section-4 of the Land Acquisition Act-1894. The landowners have also received non-litigation incentive at 20 per cent in addition to the floor rate. The NPCIL had deposited the requisite amount of Rs 460 crore in June 2012 to the state for distribution of compensation.

The first phase (2X700 MW) of the project is expected to be commissioned during 2020. Under the first phase, 2×700 MW units (1,400 MW) are proposed to be set up at an estimated cost of Rs 14,500 crore.

 

Call for endorsement- Citizens Statement Demanding Independent Enquiry into Koodankulam Safety


Please find below the citizens statement on Koodankulam drafted by Mr.Praful Bidwai and Mrs. Lalita Ramdas.

In thelight of recent news arrest of the Russian supplier ZiO-Podolsk chieffor a scam related to sub-standard equipments, the statement callsfor an independent enquiry into the plant’s safety issues, somethingthat the people’s agitation has been demanding from day one. Theformer chairman of India‘s Atomic Energy Regulatory Board has alsodemanded a moratorium on the reactor pending an independent enquiry.

Thestatement also appeals for transparency on vital safety issues inKoodankulam.

Pleasealso forward the statement to your friends for endorsement and urgethem to send back the signatures to 

 

pksundaram@gmail.com

 

With bestregards,
AchinVanaik

P KSundaram

Coalitionfor Nuclear Disarmament and Peace

www.cndpindia.org

 

Citizens Statement Demanding Independent Enquiry into Koodankulam Safety

 

Recent developments in Koodankulam, which highlight grave technology-related problems with the first nuclear reactor, take the shocking failures of the operator, Nuclear Power Corporation, to a new low.

The Atomic Energy Regulatory Board was forced to admit to the existence of sub-standard and unsafe equipment in the reactor only after a major scandal concerning a Russian sub-supplier firm was brought to light by the ongoing people’s movement against the project. However, the admission came only after the nuclear establishment’s denial tactic manifestly failed. Former AERB Chairman Dr. A. Gopalakrishnan has unequivocally and publicly opposed the commissioning of the plant and trashed the AERB’s admission and assurances.

We urge that an independent enquiry must be conducted into the safety aspects of the Koodankulam reactors, including the supply of sub-standard equipment, vulnerability of the reactor pressure vessel,and the fraudulent post-dated environmental clearance given to the desalination unit. Till then, a moratorium on the reactor’s start-up must be imposed in Koodankulam.

AERB’s sloppy sarkari reply on Koodankulam


People’s Movement Against Nuclear Energy (PMANE)
Idinthakarai & P. O. 627 104
Tirunelveli District, Tamil Nadu
Phone: 98656 83735; 98421 54073
April 19, 2013
koodankulam@yahoo.com

Untrustworthy AERB and Its Sloppy Sarkari Reply for the Koodankulam Fiasco

The Atomic Energy Regulatory Board (AERB) has finally woken up, it
seems. They have just acknowledged with great awkwardness: “…during
testing of thousands of valves installed in the plant, the
performances of four valves of a particular type were found deficient.
As corrective measures, the valve components are being replaced by
NPCIL and their performance is further being subjected to regulatory
review. Subsequent clearances will be granted by AERB only after a
satisfactory review.”

So, according to the AERB, it is a simple problem of just four valves
malfunctioning in the Koodankulam Nuclear Power Project (KKNPP). What
an irresponsible and disingenuous explanation to a very complex and
dangerous problem that is deeply mired in corruption, theft,
wastefulness, shoddiness and sheer inefficiency.

No one in India can have any kind of trust and confidence in the AERB
anymore. We would bring the attention of the Indian citizens to the
Comptroller and Auditor General’s Report No. 9/2012-13 on the
“Activities of Atomic Energy Regulatory Board” published in August
2012. It pointed out so many flaws and problems in the regulatory
mechanism of the atomic energy establishment in India.

This discredited agency’s sloppy sarkari reply begs many more
important questions:

[1] Were the first and the second “hydro tests” at KKNPP complete
failures then? Why doesn’t the AERB say anything about these tests?

[2] How did the AERB give clearance to the “initial fuel loading”
(IFL) with all these four valves malfunctioning?

[3] The PMANE posed the following question to AERB on January 28, 2013:
“Zio-Podolsk, owned by the Russian company Rosatom, is under
investigation in Russia for shoddy equipment it produced for several
nuclear plants in that country and abroad since 2007. It is suspected
that Zio-Podolsk used wrong type of steel (cheaper than the one
originally required) to produce equipment for nuclear plants, such as
steam generators. This company is said to have supplied several
equipment and parts to the KKNPP. Please give a list of those
equipment and parts that have been supplied by Zio-Podolsk to the
KKNPP units.”

The AERB replied on February 12, 2013 (No. AERB/RSD/RTI/Appl. No.
329/2013/2421) very evasively: “Selection of a company for supplying
any equipment to NPCIL, is not under the purview of AERB. However,
with respect to Quality Assurance (QA) during design, construction,
commissioning and operation, a set of well established AERB documents
on QA Codes and Guides are published and they were followed during the
safety review of KKNPP.”

If the “well established AERB documents on QA Codes and Guides … were
followed during the safety review of KKNPP,” how did the AERB team
fail to find out about these four valves earlier? Which AERB officials
are responsible for this valve malfunctioning oversight? Why did the
AERB have to wait until the former AERB chief, Dr. Gopalakrishnan,
spoke about the Koodankaulam project?

[4] Mr. R. S. Sundar, the site director of the KKNPP, has claimed that
“the NPCIL had placed orders for obtaining a range of components for
KKNPP from LG Electronics, South Korea, Alstom and VA Tech, France and
Siemens, Germany, apart from getting components from Russia” (P.
Sudhakar, “Kudankulam plant Director denies allegation,” The Hindu,
April 4, 2013). Although he lists all these foreign companies and
their host countries, Mr. Sundar carefully avoids the names of
Zio-Podolsk and Informteck from Russia. Does the AERB consider the
KKNPP as a Russian project or an international collaboration project?
Does the AERB have the complete list of all these various parts and
equipment? How were the “well established AERB documents on QA Codes
and Guides” followed during the safety review of all these various
parts and equipment from all different sources?

[5] Dr. M. R. Srinivasan, the former chief of the Atomic Energy
Commission, has publicly acknowledged now: “We sought an additional
safety mechanism well before the Fukushima disaster. The safety
mechanism consists of valves. The original reactor design had to be
altered and I feel this is the basic cause for delay.” According to
him, the valves were designed partially in India and Russia and
compatibility with the reactor led to some hiccups
(http://newindianexpress.com/states/tamil_nadu/article1517314.ece).
Did the AERB authorize the alteration of the “original reactor
design”? If so, when did the AERB authorize it? What authorization
procedure was followed? And who in the AERB authorized the later
“refit” in the reactor? What was this “refit” all about?

[6] Izhorskiye Zavody, which is part of United Machinery Plants (OMZ)
holding, signed a contract with India for the construction of two
nuclear reactor bodies for Kudankulam’s station in 2002. They shipped
a new nuclear reactor body that would be the first power unit of
India’s Kudankulam nuclear power plant to the city’s sea port. Yevgeny
Sergeyev, general director of Izhorskiye Zavody, said at a ceremony
sending off the reactor: “We were so sure of our partners that we
started to produce the first reactor bodies four months before the
official contract was signed.” Sergeyev said the reactor was completed
six months before deadline (The St Petersburg Times, 19 November 2004,
http://sptimes.ru/index.php?action_id=2&story_id=2135). How were the
“well established AERB documents on QA Codes and Guides” followed
during the safety review of the reactor bodies? Is that why we found
belt-line welds much later in the RPVs in sharp contrast to the
original
design?

The Federal Service for Ecological, Technological and Nuclear
Supervision, Rostekhnadzor, claimed in 2009: “The main causes of
violations in the NPP construction works are insufficient
qualifications, and the personnel’s meagre knowledge of federal norms
and rules, design documentation, and of the technological processes of
equipment manufacturing. In particular, the top management of
Izhorskiye Zavody [supplier of RPV] have been advised of the low
quality of the enterprise’s products and have been warned that
sanctions might be enforced, up to suspending the enterprise’s
equipment production licence”
(http://www.gosnadzor.ru/osnovnaya_deyatelnost_slujby/otcheti-o-deyatelnosti-sluzhbi-godovie/).

As Dr. A. Gopalakrishnan has pointed out in response to the AERB’s
sloppy sarkari reply, “the AERB comes up with a very minimal and
partial admission. Their clarification has left out many other flaws,
including potential corrupt practices, lack of adequate quality
assurance, and total & unnecessary secrecy in safety regulation of
civilian nuclear plants.”

To sum up tersely, the AERB has no integrity or credibility and should
call off the Koodankulam project completely instead of explaining away
the dangerous issues involved in the project and making us all guinea
pigs to test the Indian nuclear establishment’s corruption,
inefficiency and black market procurement practices.

The Struggle Committee
The People’s Movement Against Nuclear Energy (PMANE)

 

Koodankulam Must Be Stopped: Dr. A Gopalakrishnan #nuclear


DiaNuke

Dr. A Gopalakrishnan, the former Chairman of India’s Atomic Energy Regulatory Board, has raised some urgent issues in his article in the New Indian Express today that the government must address before commissioning Koodankulam.

Please click on the picture to read the article in the E-paperPlease click on the picture to read the article in the E-paper

The first of the two 1000 MWe VVER nuclear reactors at Koodankulam Project (KKNP-1), under commissioning and testing , is supplied by the Russian atomic energy corporation, Rosatom ,through its subsidiary, Atomstroyexport. On the Indian side , the KKNP project is owned by the Nuclear Power Corporation of India Limited (NPCIL) , a public sector undertaking of the Department of Atomic Energy (DAE) . The overall safety regulation responsibility is with the Atomic Energy Regulatory Board (AERB) .

Crucial materials and reactor parts have been exported to KKNP-1 & 2 by a Russian government-owned company called Machine-Building Plant ZiO-Podolsk (ZiO) , which is another Rosatom subsidiary. ZiO-Podolsk supplies have been sent for years to all the Russian nuclear power plants, and to most of the VVER plants exported to countries like India, Iran, China and Bulgaria. These include important safety subsystems , equipment , components and materials supplied over the years to KKNP-1 & 2 .

KKNP-1 was originally scheduled to start operation in early 2010 , but presently even the final start-up testing is not completed . In January 2013 , the Secretary, DAE, stated that he was totally certain that the reactor would be started that month itself, but it did not happen.

From NPCIL’s continuing inability to start-up KKNP-1 till now , it is very obvious that the Indo-Russian commissioning team at Koodankulam is facing some serious problems which they never anticipated.

The congenital lack of transparency from which the Prime Minister’s Office (PMO) and the nuclear sector organisations are suffering always prevents the public from knowing the real story. The DAE Secretary’s reasons for the delay in KKNP-1 start-up is that “ the engineers have opened up a few of the valves and such components for maintenance and it’s taking some time.” M.R Srinivasan, Member (AEC), is reported to have said, “We sought an additional safety mechanism , which consists of valves. The original reactor design had to be altered and I believe this is the basic cause for delay . The valves were designed partially in India and Russia and compatibility with the reactor led to some hiccups.”

The fact that a high-cost , high-risk nuclear reactor is facing defects and deficiencies in its components and equipment even before it is started up is highly unusual, and this indicates gross failures at several levels in the DAE-AERB-NPCIL-Atomstroyexport combine.

If designs have been checked and followed , procurement of materials and fabrication have been done as per technical specifications, testing and quality control at the manufacturer’s shops were comprehensive, and NPCIL’s Quality Assurance (QA) before acceptance of supplies at site were strictly as per nuclear norms, these problems could not have arisen at the commissioning stage.

If news trickling out of KKNP-1 site is to be trusted, the Russian special check valves in the passive long-term core flooding system (hydroaccumulator system- stage 2) are defective as received and, at this late hour an order to manufacture one or more such valves has been placed on a reputed Hyderabad company. One or more of the new Russian valves show cracks even at the finish of initial commissioning tests. Similarly, the passive heat removal system (PHRS) is not functioning as per specifications, because the damper — air heat exchanger — vane system has not been integrally tested at the Russian manufaturer’s works as required and problems were not sorted out there itself . There are other problems to list, but the above are typical of the flaws holding up the reactor commissioning. Almost all these malfunctioning components and sub-systems have been produced by ZiO-Podolsk, and all of them are crucial to the safety of the plant, under beyond-design-basis accidents.

The Bellona Foundation, an international environmental NGO based in Norway
(), stated (http://www.anti-atom.ru/en/node/3468 ) in February 2012 that the Russian Federal Security Service (FSB) had arrested Sergei Shutov, the procurement director of ZiO-Podolsk, on charges of corruption and fraud. The FSB has charged Shutov with buying low-quality raw materials on the cheap over the years, passing them off as high-quality materials, and pocketing the difference.

It is not clear how many reactors have been impacted by this alleged crime, but reactors built by Russia in India, Bulgaria, Iran and China are among those suspected to have received sub-standard equipment and components, given the timeframe of work completed.

Bulgaria has already asked Atomstroyexport and ZiO-Podolsk to provide details of materials used in their reactors, including quality certificates. Similarly , China’s Tianwan plant has two VVER-1000 reactors, and the Chinese have raised several hundred queries regarding the low quality of materials and components.

Investigative Journalists, an NGO based in the Armenian capital, has said that the use of substandard materials could lead to a nuclear disaster. “Stopping and conducting full scale checks of reactors where equipment from ZiO-Podolsk has been installed is absolutely necessary,” Vladimir Slivyak, co-chair of Russian environmental NGO Ecodefence, said recently.“Otherwise the risk of a serious accident at a nuclear power plant, whose clean-up bill, stretching into the tens and even hundreds of millions of dollars, will have to be footed by taxpayers.”

The problems with ZiO-Podolsk supplies to the KKNP-1 Project, seen in the context of the widespread allegations of corruption and poor quality, indicate that the root cause of KKNP-1 problems lies in those sub-standard supplies. Recent questions raised under RTI to the AERB and NPCIL resulted only in evasive and pointless replies. Asked about parts supplied by ZiO, AERB says “the selection of a company for supplying any equipment to NPCIL is not under the purview of AERB.” For the same query, NPCIL says, “No information regarding any investigation against ZiO-Podolsk is available to NPCIL”. Both these DAE organisations were lying in these replies, as is evident from the following facts.

The website of the Russian Embassy in India carries the news of a senior Indian delegation headed by AP Joshi, Special Secretary, DAE having visited ZiO-Podolsk from July 15-18, 2012, just about five months after the arrest of Sergei Shutov, Zio-Podolsk’s Procurement Director, for fraud and corruption in sending out inferior products to national and foreign reactor projects , including KKNP-1 & 2.

The Indian Embassy in Moscow and the NPCIL / DAE personnel stationed there must have certainly known about Shutov’s arrest , and the inherent serious implications of his actions on the safety of KKNP-1 & 2. They would have briefed the DAE Secretary about it immediately and through him the PMO would also have been alerted . And yet , both AERB and NPCIL pretend to take the ZiO-Podolsk matter very lightly and feign ignorance .

One can only surmise that the PMO & the DAE quickly realied the gravity of the potentially explosive situation that could develop vis-a-vis Koodankulam reactor safety, following Shutov’s arrest, because by then several crucial equipment, components and materials with alleged poor quality and deficiencies have been already installed in various parts of both units at KKNP and Unit-1 was on its way to commissioning. The PMO & DAE seem to have decided to weather the storm through the joint execution of an Indo-Russian cover-up plan, and hold a firm position that all is well with KKNP supplies.

After a fire-fighting strategy was framed in India , it would appear that the PMO despatched the Special Secretary, DAE, and his team to visit ZiO-Podolsk and spent three days to firm up the modus operandi of tackling the rather tricky situation which could develop in India once the protesters and the courts of law come to know of the scam details. After all , the PMO’s top priority is to meet the PM’s promise to President Putin that KKNP-1 will be started up in April 2013, and public safety and corruption come only after that .

There could be a large number of equipment, components and materials of substandard quality from ZiO-Podolsk already installed in various parts of KKNP-1& 2 whose deficiencies and defects are dormant today, but these very same shortcomings may cause such parts to catastrophically fail when the reactor is operated for some time .

Many such parts and materials may have been installed within the reactor pressure vessel itself, which is now closed and sealed in preparation for the start-up. Once the reactor is made critical and reaches power operation, much of these components and materials inside will become radioactive and/or will be in environments where they cannot be properly tested for quality or performance.

Under the circumstances , KKNP Unit-1 commissioning and KKNP-2 construction work must be stopped forthwith, and there can be no question of resuming these works towards start-up of both these reactors until a thorough and impartial investigation is carried out into the impact of this corruption scandal and sub-standard supplies on the safety of these reactors.

And these investigations must be carried out by a team, where majority membership must not be from DAE , NPCIL and AERB, but include subject experts from other organisations in the country.

India must also seriously consider inviting an IAEA expert team specially constituted to investigate the specific issues which this scandal has thrown up.

 